  Dublin Port, Alexandra Road, Dublin 1

Jul 27 2021

Application Received

Sep 20 2021

Further Info. Requested

Nov 11 2021

Further Info. Received

Jan 14 2022

Decision Due

Jan 14 2022

Decision

Feb 14 2022

Appeal Submitted

Jul 19 2023

Granted

Jul 19 2023

Appeal Decision
  • Submitted to Dublin City Council, 27 / 07 / 2021
  • Application Type: Permission
  • Current Status: Appeal Decided
  • Decision Text: GRANT PERMISSION
  • Decision Summary: Granted
Decision Appealed:
  • Appeal Submitted: 14 / 02 / 2022
  • Appeal Decision: GRANT PERMISSION (19 / 07 / 2023)
-- View Live Map (full screen map - includes planning application boundaries, zonings & other planning-related mapped content)

-- Signup Now to link to Commencement Notice details
Development:
PROTECTED STRUCTURE: Permission for development at this site which extends from North Wall Quay Extension to the Tolka Estuary, to include the western boundary to Dublin Port and pavements along East Wall Road, across the Alexandra Road junction with East Wall Road, across the Tolka Quay Road junction with East Wall Road, Bond Road, across the Promenade Road junction with Bond Road and to end of Bond Road, Dublin Port, Dublin 1 & 3 and permission to amend development permitted under Reg. Ref. 3084/16. The ESB substation (Record of Protected Structures No. 8771) is located within the subject site. The proposed development will consist of construction of a new 1.4km pedestrian walkway and a 2-way cycle lane along East Wall Road and Bond Road from the River Liffey to the Tolka Estuary and will comprise the following: • Removal of part of existing Dublin Port western boundary wall / fence; • Removal of the existing access to Terminal 3 on East Wall Road; • Modifications to layout of Terminal 3 along eastern boundary including removal of private car parking spaces; • Relocation of 3 no. existing double billboards; • Relocation of existing flagpoles, • Relocation of existing temporary office building of 15sq.m; • Closure of left turn from Alexandra Road to East Wall Road southbound; • Removal of 17 no. car parking spaces from the Dublin Port Centre car park; • Realignment of Bond Road north of the Promenade Road junction; • Construction of new boundary along sections of the Dublin Port western boundary comprising railings over plinth or wall to a height of c. 4m along East Wall Road and Bond Road or for a section along Bond Road a wall of c. 2.6m in height; • Creation of a civic space adjacent to the River Liffey at North Wall Quay Extension, • Provision of 25 no. bicycle parking spaces, • Provision of a Dublin Port Irish language installation as part of the boundary treatment adjacent the Crane 292 enclosure. • Provision of hard and soft landscaping including trees along the extent of the route, amenity, interpretation and wayfinding fe... Signup to read full development description
This planning file was referred to An Bord Pleanála.
You can view ABP information by signing up for a PlanningAlerts.ie account. Signup Now...
An Bord Pleanála Information:
Creative Commons LicensePlanning Data is published by Department of Housing, Planning and Local Government and is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

  • Distance: Received: Decision: Development Address: Development Description:
    170m 12/08/2024 GRANT PERMISSION Port Centre, Alexandra Road, Dublin Port, Dublin 1 D01H4C6 Permission for development will consist of refurbishment, renovation and retrofitting works to an existing building (Dublin Port Centre and associated ancillary works, comprising: Reglazing and insulation upgrades to all building facades to include installation of louvres (brise soleil type); Revisions at roof level to include replacement of existing roof slab, construction of enclosed viewing gallery (c. 36sq.m) and open-air external accessible deck, reconfiguration of existing plant areas and antennae and provision for plant relocated from fifth floor level, all resulting in a revised total building height (excluding antennae) of c. 36.25m (increased from 34.15m) and a reduction of 39sq.m in gross floor area (GFA) to 60sq.m total; Removal of existing signs (2 no. signs of 9.2sq m each) on the northern and southern façades and provision for 3 no. illuminated corporate signs (combined C. 42.5sq.m) at roof level on the northern, southern and western facades; Internal layout modifications to provide... login required. Details...
    360m 11/07/2024 GRANT PERMISSION Units MSU2,7,30,36,37,38,39,40,41,42,43 and 45, First and Second Floor,, Point Village District Centre, East Wall Road and Sheriff Street Upper, Dublin 1 PERMISSION : The development consists of the amalgamation and/or change of use of existing units located at first and second floor level, from previously permitted retail and retail/ café to leisure use as set out below: Unit 7 - change of use from permitted café/ retail use to leisure use at both first and second floor level with an overall area of c.402 sq.m. Unit 30- change of use from permitted retail use to leisure use at both first and second floor level with an overall area of... login required. Details...
    470m 20/06/2024 GRANT PERMISSION The Freight Building, Lands which form part of the former Castleforbes Business Park , Sheriff Street Upper , Dublin 1 Permission for development at the existing commercial office building known as 'The Freight Building' on lands which form part of the former Castleforbes Business Park, Sheriff Street Upper, Dublin 1. The site is bound by Sheriff St Upper to the south, CIE railyard to the north and east, and wider former Castleforbes Business Park (under c... login required. Details...
    330m 26/04/2024 APPLICATION WITHDRAWN On the public footpath outside the Telus Building on East Wall Road, near the junction with Sheriff Street, Dublin 1 Apply for planning permission for the installation of a double-sided digital Metropole advertising display and associated works and services on the public footpath outside the ‘Telus’ Building on East Wall Road, n... login required. Details...
    330m 16/02/2024 APPLICATION DECLARED INVALID On the public footpath outside the Telus Building on East Wall Road, near the junction with Sheriff Street, Dublin 1 To apply for planning permission for the installation of a double sided digital Metropole advertising display and associated works and services on the public footpath outside the ‘Telus’ Building on East Wall Road, ... login required. Details...
    400m 14/12/2023 GRANT PERMISSION Point Village District Centre and Point Square, East Wall Road, and Sherriff Street Upper, Dublin 1. The proposed development relates to: 1) Permission for the change of use of Unit 6 (c. 109 sq.m) from permitted retail/ café use to office use to provide for a new office entrance lobby for commercial offices above; 2) The removal of the existing Conference Centre Entrance, glass canopy, access control pedestal, signage, and small totem, on East Wall Road. 3) The replacement of the revolving door at the existing office entrance on East Wall Road with a double glazed door, and the removal of an access control pedestal and small totem; 4) Removal of vacant substation and switch rooms, and existing recessed glazed and metal louvre clad façade, on East Wall Road, to be replaced with a new glazed façade in line with the existing external columns, resulting in an increase in floor area of 38. sq.m. 5) Internal layout reconfiguratio... login required. Details...
    470m 04/10/2023 GRANT PERMISSION A site generally bounded by Alexandra Road to the north, Branch Road No.1 and rail line to the west,, Branch Road No.3 to the east and Alexandra Basin to the south, at Dublin Port, Dublin 1, which includes R&H Hall Silo Building (a protected structure, re PROTECTED STRUCTURE: PERMISSION:The development will consist of: A. Demolition and removal of existing quayside overhead bulk material conveyor system (2no. North/South and 1no. East/West), 2no. associated elevator/weighing towers, redundant transformer building and weighbridge and associated infrastructure to include site clearance of redundant walls, plinths and fences; B. Reinstatement of window opening to the R&H Hall Silo Building, a protected structure, following removal of the elevated conveyor system (within its curtilage) together with internal and external repair works to the remainder of the building; C. Relocation of existing rail line northwards to a safe zone set further back from the quayside, existing crane rails along the quayside and existing 30m high mast lighting (HML) tower; D. Relocation of existing reefer gantries and 30m HML towers located at McCairn's Yard and provision of 2no. new reefer gantries; E. Quayside and yard pavement upgrades and reinforcement works and installation of new 30m HML towers; F. Construction of a new bulk product silo facility at McCairn's Yard, to include intake/outtake of bulk product from vessels to quayside storage and onward transport. The facility will consist of 6no. bulk product storage silo bins c.30.0m in height (... login required. Details...
    330m 08/09/2023 GRANT PERMISSION Dunnes Stores, The Anchor Unit 1 of the Point Village Shopping Centre, Dublin 1 PERMISSION:To consist of the provision of alcohol off-licence sales as part of the existing retail premises at the ground floor (level 0) including all ass... login required. Details...
    480m 27/01/2023 GRANT PERMISSION Unit 2, The Liffey, Point Campus, North Wall Avenue, Dublin 1, D01T2NO PERMISSION: For a) change of use from shop to use as a restaurant and takeaway with delivery service, b) new fascia signage over entrance door, and c) alterations to existing shopfront to accomodate ventilation services.... login required. Details...
    460m 20/12/2022 APPLICATION DECLARED INVALID Unit 2, The Liffey, Point Campus, North Wall Avenue, Dublin 1 Permission for (a) change of use from shop to use as a pizza restaurant and takeaway with home delivery service, (b) new fascia signage over entrance door, (c) alterat... login required. Details...
    430m 24/11/2022 GRANT PERMISSION Promenade Road, Dublin Port, Dublin 1 Permission for change of use, material alterations and extension to an existing two storey office building and part of 2no. industrial sheds for use as Artist Workspaces on a site at Promenade Road, Dublin Port, Dublin 1. The development will consist of a) Material alterations to the existing two storey office building to provide a ground, first and second floor extension of 30.4 sqm area total, to include a passenger lift providing access to first floor. Material alterations to the north, south, east and west facades by closing up 19no. windows and 1no. door, enlarging 2no. existing window openings to the south and west facade and 1no. new window to the west facade, provide external cladding to all facades with an entrance canopy to the west elevation and fixed signage to the north elevation b) Material alteration... login required. Details...
    490m 17/10/2022 GRANT PERMISSION 123, The Seabank House, East Wall Road, East Wall, Dublin 3 Permission for retractable awning above existing outdoor seating area, to front of existing public house.... login required. Details...
    420m 21/09/2022 GRANT PERMISSION AND RETENTION PERMISSION Site which extends from Promenade Road, to Alexandra Road, Dublin Port, Dublin 3 PERMISSION & RETENTION: Development at this site which extends from Promenade Road to Alexandra Road and includes the western part of Circle K Fuel Terminal1, part of Promenade Road at its junction with Terminal 10 Link Road (T10 Link Road), T10 Link Road, part of Tolka Quay Road, No. 1 Branch Road North and part of Alexandra Road. It also incorporates land comprising parts of Terminal 4 and Terminal 4 North, all at Dublin Port, Dublin 1. 1. Retention permission is sought for development of part of a link road known as T10 Link Road connecting Promenade Road with Tolka Quay Road to the west of the Terminal 10 State Services yard. The road and associated infrastructure comprises of: - An approximately 125 metre long and 14.4 m wide two-way road (two northbound lanes and one southbound land), with 2 no. 3m wide footpaths. - A T-junction with Promenade Road; - A pedestrian zebra crossing at the northern end of the link road; and - A vehicular entrance to the Terminal 10 state services yard; - Revisions to fenceline previously permitted under Reg.Ref. 4483/19 at northeast corner of Terminal 4 North boundary; and - All associated ancillary works including site clearance, demolitions, earthworks, pavement construction, drainage services, diversion and installation of utility services, installation of road markings and signs, lighting, CCTV and associated boundary fencing. Permission is sought for development which will consist of a new link road from north of Tolka Quay Road to Alexandra Road. The new link road and associated infrastructure will comprise of: - An approximately 250m long two-way road (two north bound and two south bound lanes) with 3 m wide footpaths on either side of the road and two-way segregated cycleway on eastern side of road; - New roundabout, connecting proposed new link roa... login required. Details...
    420m 13/09/2022 APPLICATION DECLARED INVALID Promenade Road to Alexandra Road, Dublin Port, Dublin 1 PERMISSION AND RETENTION PERMISSION for development at this site which extends from Promenade Road to Alexandra Road and includes the western part of Circle K Fuel Terminal 1, part of Promenade Road at its junction with junction with Terminal 10 Link Road (T10 Link Road), T10 Link Road, part of Tolka Quay Road, No.1 Branch Road North and part of Alexandra Road. It also incorporates land comprising parts of Terminal 4 and Terminal 4 North all at Dublin Port, Dublin 1. Retention permission is sought for development of part of a link road known as T10 Link Road connecting Promenade Road with Tolka Quay Road to the west of the Terminal 10 state services yard. The road and associated infrastructure comprises of : An approximately 125 metre long and 14.4m wide two-way road (two northbound lanes and one southbound lane), with 2 no. 3m wide footpaths; a T-junction with Promenade Road; pedestrian zebra crossing at the northern end of the link road; a vehicular entrance to the terminal 10 state services yard; revisions to fenceline previously permitted under reg. ref. 4483/19 at northeast corner of terminal 4 north boundary; all associated ancillary works, including site clearance demolitions, earthworks, pavement construction, drainage services, diversion and installation of utility services, installation of road markings and signs, lighting, CCTV and associated boundary fencing. Permission is sought for development which will consist of a new link road from north of Tolka Quay Road to Alexandra Road. The new link road an associated infrastructure will comprise of : approximately 250m long two way road (two north bound and two south bound lanes) with 3m wide footpaths on either side to the road and two-way segregated cycleway on eastern side of road; new roundabout, connecting proposed ... login required. Details...
    370m 06/09/2022 GRANT PERMISSION Dunnes Stores, The Point Square Shopping Centre, East Wall Road, Dublin 1 Planning permission for the provision of alcohol off-licence sales as part of the existing retail premises at the ground floor of the Point Square Shopping Centre, East Wall Road, Dublin 1.... login required. Details...
    420m 29/08/2022 APPLICATION DECLARED INVALID Promenade Road to Alexandra Road & incl. part of Promenade Road at its junction with Terminal 10 Link Road, part of Tolka Quay Road, No. 1 Branch Road North & part of Alexandra Road, Dublin Port, Dublin 1. PERMISSION and RETENTION PERMISSION: Development at a site which extends from Promenade Road to Alexandra Road and includes part of Promenade Road at its junction with Terminal 10 Link Road (T10 Link Road), T10 Link Road, part of Tolka Quay Road, No. 1 Branch Road North and part of Alexandra Road. It also incorporates land comprising parts of Circle K Fuel Terminal 1 and Terminal 4 and Terminal 4 North, all at Dublin Port, Dublin 1. Retention permission is sought for development of part of a link road known as T10 Link Road connecting Promenade Road with Tolka Quay Road to the west of the Terminal 10 State Services yard. The road and associated infrastructure comprises of: - An approximately 125 metre long and 14.4m wide two-way road (two northbound lanes and one southbound lane), with 2 no. 3m wide footpaths; - A T-junction with Promenade Road; - A pedestrian zebra crossing at the northern end of the link road; and - A vehicular entrance to the Terminal 10 state services yard; - Revisions to fenceline previously permitted under Reg. Ref 4483/19 at northeast corner of Terminal 4 North boundary; and - All associated ancillary works, including site clearance, demolitions, earthworks, pavement construction, drainage services, diversion and installation of utility services, installation of road markings and signs, lighting, CCTV and associated boundary fencing. Permission is sought for development which will consist of a new link road from north of Tolka Quay Road to Alexandra Road. The new link road and associated infrastructure will comprise of: - An approximately 250m long two-way road (two north bound and two south bound lanes) with 3m wide footpaths on either side of the road and two-way segregated cycleway on eastern side of road; - New roundabout, connecting proposed new link road with T... login required. Details...
    490m 27/07/2022 GRANT PERMISSION The Exo Building, North Wall Quay , (D01 W5Y2) and at the junction of North Wall Quay and East Wall Road , Dublin 1 The proposed development will consist of: i. The installation of an exterior totem sign (overall height of 5.45m and width of 1.6m) with a curved LED screen, situated at the corner of East Wall Road and North Wall Quay; ii. The installation of a Mobius structure (overall height of 3.48m and wi... login required. Details...
    470m 11/07/2022 GRANT PERMISSION A site of 0.5 hectares, which previously formed part of the Castleforbes Business Park, Sheriff Street Upper, Dublin 1 A site of 0.5 hectares, which previously formed part of the Castleforbes Business Park, Sheriff Street Upper, Dublin 1., The site is bound by Sheriff Street Upper to the south, Iarnrod Eireann Rail Yard to the north and east, and Castleforbes Business Park. Permission for development of 6 no. illuminated external signs and building facade lighting. This external signage and lighting application relates to a previously permitted development (Dublin City Council Reg Ref 3433/19 amended by Reg Ref 3197/20 and Reg Ref 2255/21) currently under construction. The proposed development relates to the permitted hotel element of the development only. The proposed development... login required. Details...
    310m 30/06/2022 GRANT PERMISSION Tolka Quay Road, Dublin Port, Dublin 1 The development will consist of the continuance of use of a 100m long 6.5m wide single lane bridge with access ramps over the M50 and a storage area for imported cars and vans and all associated site development and service works as permitted under planning reg. ref. 2495/17 and reg. ref. 3788/11.... login required. Details...
    450m 24/06/2022 GRANT PERMISSION Karlton Barbers, Unit 1, Block 2 Island Key, Off East Road, East Wall, Dublin 3 Planning permission is sought to divide existing retail unit into two and form new separate shopfront to second unit at Karlton Barbers.... login required. Details...
  • Geology & Groundwater
    Creative Commons LicenseContains Irish Public Sector Data (Geological Survey) licensed under a Creative Commons Attribution 4.0 International (CC BY 4.0) licence.

    Aquifer:
    • Category: Ll
    • Description: Locally Important Aquifer - Bedrock which is Moderately Productive only in Local Zones

    Vulnerability:
    • Unit Name: Lucan Formation
    • Description: Dark limestone & shale (`calp)
    • Labels: CDLUCN / LU

    Bedrock:
    • Low ( L)

    Planning & Development

    Zoning:
    Creative Commons LicenseZoning Data is published by Department of Housing, Planning and Local Government and is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.
    • No Results...

    National Parks & Wildlife (NPWS)
    Creative Commons LicenseNPWS Data is published by National Parks and Wildlife Service, Department of Arts, Heritage and the Gaeltacht and is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

    Special Area of Conservation:
    • No Results...

    Special Protection Areas:
    • No Results...

    Natural Heritage Areas:
    • No Results...

    Proposed Natural Heritage Areas:
    • No Results...

    Heritage & Conservation
    Creative Commons LicenseMonument & NIAH Building Data is published by National Monuments Service, Department of Arts, Heritage, Regional, Rural and Gaeltacht Affairs and is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

    National Monuments:

    National Monuments within 100m of the mapped planning point

    • No Results...

    National Monument Zones of Notification:

    Is this Planning Point is within a National Monument Zones of Notification? (Section 12 National Monuments Acts 1930 to 2004)

    • No Results...
    National Inventory of Architectural Heritage:

    NIAH Locations within 100m of the mapped planning point

    Name NIAH Ref # Rating / Period Original Use Current Use Protected Structure
    No Results...

    Roads & Infrastructure

    National Roads & Motorways within 500m of mapped planning point


    National Roads (N) and Motorways (M):
    • M/N50

Return to top...